A negative cost variance combined with a negative schedule variance is an indicator of

Respuesta :

Kalahira
Kalahira Kalahira
  • 27-11-2017
Cost variance and schedule variance are indicators of efficiency of a project. Therefore if you have a negative cost variance and a negative schedule variance, then the project is inefficient and you should look into ways to cut costs and save money.
Answer Link

Otras preguntas

Physical Science- 5 Questions- Please Help! 1. *What type of energy gives you the energy to ride a bike up a hill?* 25,000J 4 m/s 75 kg 20,000 J potential ene
¿Qué traje es más caro? el traje azul el traje negro el traje café el traje rojo
Two ships leave a harbor at the same time. One ship travels on a bearing S11°W at 14 miles per hour. The other ship travels on a bearing N75°E at 9 miles per ho
give one argument in favor of the tea act and one argument against the tea act
Why does Winston have conflicting emotions when he sees the dark haired girl from the fiction department fall down
Which of the following statements about federal student loans is TRUE
What did scientists believe was the cause of the hole in the ozone layer? a. cars b. aerosol sprays c. acid rain d. pump spray bottles
You should conduct preliminary research before choosing your research topic. True False
**PLEASE HELP! HISTORY!**
Which aspect of Anse's narration from As I Lay Dying most clearly makes him an unreliable narrator? A. His ideas about why Addie is dying B. His insistenc