If it takes 3 days for 10 workers to finish building one house, how many days will it take 15 workers to finish 4 houses?

Respuesta :

sirinda
sirinda sirinda
  • 19-10-2017
a = house
3 days x 10 worker = a
a = 30 work unit
4a = 120 work unit
120 work unit = 15 workers * y days
y = 120/15 = 8 days

i hope this isn't too confusing 
Answer Link

Otras preguntas

How does the contour plowing technique conserve soil?
What is the correct order of the four turning points (revolutions) in world history? A stone, industrial, agricultural, technological B agricultural, stone, te
In the Vedic Age trade was limited because of__. A. isolationism, causing people not to trade with each other . . B. poor roads, causing people to use the ri
You may be able to save time by using your existing knowledge of common word parts to figure out the definition of many words. Which word does NOT have a common
is smell a short e sounds
For which of these does mRNA provide the code? A.. DNA B.. proteins C.. gametes D.. organelles
What led to the defeat of the communist party in Czechoslovakia? . A. a coup d'etat . B. student and popular protests . C. the Solidarity Party . D. the fall o
True or False? The nuclear product of radioactive decay is called the offspring nuclide.
amos has 12 action,15 comedy,and 9 drama DVDs find the ratio of action DVDs the total number of DVDs then explain its meaningI need it now
Don't wanna sound stupid but, what is 37/9 as a mixed fraction in simplest form?