Joshua is a new project manager. He is unsure of how much time a new task will require to be completed on the project. He decides to use ________ to estimate a realistic time frame for the task.

Respuesta :

HANicole HANicole
  • 18-07-2022

Answer: PERT

Explanation:

Answer Link

Otras preguntas

Is the answer 4/5 ? Can someone help please ?
Find the area of the shape shown below. (PLZZZ HELP)
Can you explain to me the concept of a rhetorical Precis
What does Marlow mean when he says that "there is a taint of death, a flavor of mortality in lies"? BOOK: Heart Of Darkness by Joseph Conrad
Escoger Select the appropriate form of the verb. Dudo que los osos polares (polar bears) a sobrevivir (survive). Luisa está segura de que evitar la extinción de
Why Java Script uses the prefix Java in itsname?
Solve the equation 2x² + 2x + 12 = 3x² – x + 2. A. x = –5, x = –2 B. x = 2, x = –5 C. x = 2, x = 5 D. x = –2, x = 5
Let f(x) = 9x3+ 21x2^ - 14 and g(x) = 3x + 1. Find "f (x) over g (x)​
What do i write in the box?
last one for now, please please pleasse help.