A construction company can remove 3/4 tons of dirt from a construction site each hour. how long will it take them to remove 36 tons of dirt from the site? (Answer needs to be in simplest form)

Respuesta :

abdulgafaryusuf9
abdulgafaryusuf9 abdulgafaryusuf9
  • 20-11-2020

Answer:

48hours

Step-by-step explanation:

36÷(3/4)

36*(4/3)

144/3

48

Answer Link

Otras preguntas

What percentage of the 20.0 g sample does sugar (sucrose) represent?
What does the fur coat of a bear have to do with homeostasis? Pls help​
Determine the slope and the y-intercept 6y+x=6 Answer:
What can be the most threatening challenge to the federal system in Nepal? Why?
Write a paragraph that answers the questions below. Include at least two supporting details or examples. In “the literature of the Americas,” Kimberly Koza writ
1. Noah is running a portion of a marathon at a constant speed of 6 miles per hour. Complete the table to predict how long it would take him to run different di
Janine is trying to separate some ethanol from water. Which method should she use does anyone know this
What is the point in life? What would happen if the world ended right now?
From the virus’s perspective, why is the host important (Hint: Are viruses alive?!)?
does anyone know what -11<7-6w