On February 1, 2014, Nelson Corporation purchased a parcel of land as a factory site for $280,000. An old building on the property was demolished, and construction began on a new building which was completed on November 1, 2014. Costs incurred during this period are listed below: Demolition of old building $ 20,000 Architect's fees 35,000 Legal fees for title investigation and purchase contract 5,000 Construction costs 1,340,000 (Salvaged materials resulting from demolition were sold for $10,000.)
Nelson should record the cost of the land and new building, respectively, as