contestada

Crashing almost always accelerates the schedule while increasing project risk, whereas fast tracking almost always accelerates the schedule while increasing project cost.A. TrueB. False

Respuesta :

gerald4764
gerald4764 gerald4764
  • 24-01-2020

Answer: False

Explanation: Because fast-tracking doesn’t involve additional resources, it’s usually best to start with this technique while Crashing requires careful planning to prevent “panic mode” among the project crews and to avoid acceleration claims.

Answer Link

Otras preguntas

A child/teenager who is chosen to fight in the Hunger Games is called a PLZZZ HURRY!!!
I need help....read the picture pls.
11. Article 4 establishes the rules for states in the Constitution. This helps to establish the government principle of- * O Federalism O Checks and Balances O
I need help with this question.
Thirty corn seedlings of equal size were randomly assigned to one of three treatment groups. At the beginning of the experiment, the plants in group I were drie
What is the sum of the measures of the interior of any triangle
who is the prince do the ranch in mice of men?
Which of these expressions are correct variations of the Combined Gas Law?
Jacob bought some bulbs for a total of $18. The cost of each bulb was $3. How many bulbs did Jacob buy?
To solve -3x2 + 12x - 14 = 0 by graphing, you need to find the information to graph the parabola. Answer the following questions: The parabola opens upward or d