The Product Owner of a team was asked for a forecast for the completion of a product release. There were 140 story points worth of work remaining in the project. The team's average velocity in the past 3 Sprints has been 65, though the best Sprint among the last three had a velocity of 85 story points. What should the Product Owner say?