The graphic shows the schedule network diagram (in minutes) for assembling a toy train set. What is the duration of the critical path?

A) 38 minutes
B) 41 minutes
C) 49 minutes
D) 51 minutes

The graphic shows the schedule network diagram in minutes for assembling a toy train set What is the duration of the critical path A 38 minutes B 41 minutes C 4 class=

Respuesta :

chocolateandchildren chocolateandchildren
  • 26-12-2018
D because it is longer than the rest
Answer Link

Otras preguntas

whag are the major ways of keeping the eyes healthy SUB:HEALTH ​
5 1/2 + 7 3/5 + 3 1/4=
up from slavery chapter 14 summaryplease help me
Which of the following are solutions to the equation below? Check all that apply. x2 + 4x + 4 = 12
theme of ancient visayan account ​
pls help i have to do it in a graph
What is 90.125 written in word form? о A ninety-one and twenty-five hundredths r O B. ninety-one and twenty-five thousandths C. ninety and one hundred twenty-fi
please help me with this question :)​
What are social factors ?How does it plays a significant role in population growth? ​
Please help me, trying to get my grades up