A technique that uses optimistic, pessimistic, and realistic time to calculate the expected time for a particular task is called:
A. critical path method.
B. three-point estimating.
C. OPR method.
D. weighted averaging
E. expected completion time analysis.

Respuesta :

Otras preguntas

20 mL hcl HCL density of 1.18 g/mL how many grams of hcl
​________ is the possibility that the​ borrower's creditworthiness is reclassified by the lender at the time of renewing credit.​ ________ is the risk of change
I’m not sure how to do this
What are known as the properties of substances that help describe a substance yet does not change that substance? B. physical properties A. chemical properties
5. Juliette works at a department store and earns $11.20 per hour. Last week she worked 32 hours. What was her gross pay?
What are the domain and range of the function f(x) = x^4-2x^2-4?
Which type of blood vessel is the thickest?
CR Sem 2 L Pretest: Unit 1 Question 2 of 25 1 Point How does historical correlation differ from causation?
Do you know that answer ?? Help me please 9a+5=3a-1
How should you modify the graph to show the solution to the system of inequalities below? Check all that apply. Shade above 2x + y = 4. Shade below 2x + y = 4.