1.Given the following information, sketch out the network diagram.

2. Identify the different network paths through the project.

3. What is the critical path? How many days is the critical path?

Task Duration Predecessor
A 3
B 5 A
C 12 A
D 9 B
E 14 C
F 3 B
G 4 D
H 7 F, G
I 2 E, H

Respuesta :

Otras preguntas

what point does lincoln make in the gettysburg address ?
Polar bears hunt, mate, and usually make their dens on sea ice. They hunt primarily for seals that can be found near breathing holes or at places where there ar
How did Bill Clinton attract voters during his presidential campaign in 1992?
What are the 4 forces that could cause evolution to take place?
How did the domino theory influence the United States’ role in the Vietnam war?
what part of the nucleotide determines an organisms traits
Your chemistry textbook has 936 pages and weighs 4.2 pounds. your calculus textbook has 1368 pages and weighs 6.0 pounds. these books ship in cases that hold 24
Who said this: "The computer industry is the only industry that is more fashion-driven than women's fashion." Mark Zuckerberg Linus Torvalds Larry Ellison Alan
What is confucianism?
Classify the expression 7x3 as a monomial, binomial, trinomial, or polynomial